Impact Fees ▸ Investments
The City has been divided into seven districts or benefit areas, and each has a separate account. Fees collected in a district or benefit area may be used only for new construction in that area. Districts apply to arterial streets, water distribution, and parks and trails.
- Benefit Area Maps
- Water Distribution (280 K)
- Neighborhood Parks & Trails (359 K)
- Arterial Street (185 K)
- Collections and Expenditures Report
- This report has collection totals, expenditures and the remaining balance for each district. As of 08/31/18
- Parks & Trails Investments
-
The Parks & Trails impact fee can pay for: site grading and drainage, landscaping, sidewalks, play courts, basketball goals and poles, pre-fabricated shelter structures, picnic shelter pads and tables, trash receptacles, modular play structures, benches, play area matting, sand and labor.
-
Impact fee dollars for Parks & Trails have been invested in these areas:
District 1 Design, site grading and park/playground development at Ashley Heights Park 133,270 District 1 Park Improvements at Salt Creek Levee Trail 7,197 District 1 Appraisal, Property Acquisition, and design/construction of the primary walkway and pedestrian bridge for neighborhood access to the future Timber Valley neighborhood park. 274,645 District 2 Hydrologic evaluation and site design services for the future Hartland's Garden Valley Park 96,511 District 2 New picnic shelter for Stonebridge Park 17,122 District 2 Design services for the future trail underpass at Alvo Road Trail 3,267 District 2 Property Acquisition for Fallbrook Park 225,402 District 2 Design services for future trail at Landmark Fletcher Trail site 13,136 District 2 Engineering and design services for future trail extension through the Stonebridge Development. 20,843 District 2 Development of the Stonebridge Trail 84,906 District 3 New picnic shelter for Schleich Park 10,770 District 3 Engineering and design services for future trail extension through the Landmark-Fletcher area. 100,759 District 4 Property Acquisition for Waterford Park 188,964 District 5 Pipe railings and deflector boards for the Billy Wolff Trail extension 33,643 District 5 Installation of new playground and picnic shelter for Phares Park 67,551 District 5 Park improvements at Mendoza Park 2,758 District 5 Additional property acquisition for Eden Park South 109,087 District 5 Preliminary planning for future neighborhood park to be co-located with future LPS elementary school 5,580 District 6 Design and preliminary grading for the Cavett Trail connector 26,638 District 6 Sidewalk connections in Country View Park 57,989 District 6 Design services for Cavett Connector 16,090 District 6 Sidewalk Construction at Grand Terrace Park 53,106 District 6 Preliminary design and site grading and playground equipment acquisition for the future Grand Terrace neighborhood park. 244,415 District 6 Payment for purchase of future neighborhood park land (co-located with Wysong Elementary School) and development of Cavett Connector Trail 309,684 District 7 Property acquisition for the future Folsom Park site 174,213 District 7 Sidewalk connections in Densmore Park 3,922 District 7 Partial payment for purchase of future neighborhood park land (co-located with future LPS elementary school) 38,400 Total $2,319,868 As of 08/31/18
- Arterial Streets Investments
The Arterial Streets impact fee can pay for: pavement, bike trails, median landscaping, street lights, storm sewer, box culverts, retaining walls.
-
Impact fee dollars for Arterial Streets have been invested in these areas.
District 1 Design and construction of 2 Lanes Offset NW 56th from Partridge to Adams 1,010,232 District 1 Design of current and future construction for Coddington from West "A" to West Van Dorn 2,400,746 District 1 Design of 4 through lanes at West "A" / SW 40th and Coddington 1,087,680 District 1 Traffic Signal and turn lane construction at NW 48th and Huntington 118,660 District 1 Design of 4 through lanes at NW 48th, West "O" to W Adams 3,231,552 District 2 Design and construction of 4 through lanes at 14th / Superior / Alvo Rd 3,533,634 District 2 Design and construction of 2 lane offset at Fletcher / 14th / Telluride 633,721 District 2 Design of 10th Street Bridge over Salt Creek 1,384,994 District 3 Construction of additional turn lane at N 56th and Cornhusker Hwy 315,000 District 3 Design of 4 through lanes at Arbor from 40th to 56th 76,643 District 3 Design and construction of left turn lanes at 27th and Superior 419,812 District 3 Design and construction of right turn lane at 33rd and Superior 243,458 District 3 Design of 4 through lanes at Arbor from 56th to 70th & 70th from Arbor to Salt Creek 51,555 District 3 Study and capacity needs 70th and Cornhusker to 84th and Cornhusker Areas 1,788 District 3 Construction of Arterial Rehabilitation 46,853 District 3 Design and construction of additional turn lane at North 27th & Knox 138,487 District 4 Design of 2 + 1 lane section on Adams from 75th to 90th and turn lane improvements on 84th at Windmill 1,958,241 District 4 Design and construction of additional turn lane and traffic signal at 84th & Havelock 303,761 District 4 Design and construction of traffic signal at 84th and Leighton 224,536 District 4 Construction of 98th Street from Waterford Estates Dr. to Moonlight Dr. 1,712,950 District 4 Design and construction of additional turn lane at 84th & O 333,786 District 4 Design and construction of Havelock from 84th to the east 4,292 District 4 Design of Holdrege St. from 98th to Cessna Ln 61,774 District 4 Design and construction of 98th St from 'O' to Waterford 973,936 District 5 Design and construction of additional lanes on Pine Lake Road from 84th to 98th 999,314 District 5 Design and construction of three lane section of 98th street from Pine Lake Road to Old Cheney 2,943,300 District 5 Design and construction of additional turn lane and traffic signal at 56th and Elk Crest 271,081 District 5 Design of four through lanes on Van Dorn from 84th to 91st 51,920 District 5 Design and construction of four through lanes plus turn lanes on Old Cheney from 70th to 82nd 2,838,579 District 5 Design and construction of two lanes with turn lanes on 98th from Pine Lake to Yankee Hill 509,355 District 5 Design and construction of additional turn lane at 70th and A Streets 122,867 District 5 Design of A St from 84th to 98th St. 85,323 District 6 Design of 4 through lanes on 56th Pine Lake to Yankee Hill 267,186 District 6 Design of 4 through lanes on Pine Lake from 56th to Hwy 2 1,852,885 District 6 Construction of 4 lanes on Pine Lake Road from 40th to 56th 1,100,556 District 6 Installation of new traffic signal at 40th & Yankee Hill 122,067 District 6 Construction of 4 lanes on 27th South of Yankee Hill 171,638 District 6 Design of 4 through lanes at S 40th, Yankee Hill-Rokeby 178,681 District 6 Design of 4 through lanes on S. 56th from Old Cheney to Pine Lake Road 191,975 District 6 Design of 4 through lanes on S. 56th from Shadow Pines to Old Cheney 686,620 District 6 Design and grading of Rokeby Road from 70th to 91st 730,068 District 6 Design and construction of Yankee Hill Road from 70th to 81st 1,000,000 District 6 Design of 84th Street from Rokeby Road to Yankee Hill Road 80,000 District 6 Design and construction of Yankee Hill Road from 81st to Hwy 2 777,453 District 6 Design and construction of Rokeby Road from 40th to 48th Streets 30,323 District 7 Design on intersection improvements at 14th/Old Cheney/Warlick 2,862,618 District 7 Design and construction of turn lanes on Pine Lake Road between 14th and 27th 428,750 District 7 Design of 4 through lanes at 27th from Pine Lake to Yankee Hill 1,330,612 Total $39,901,262 As of 08/31/18
- Water & Wastewater Investments
The Water & Wastewater impact fee can pay for: water supply, treatment, transmission mains, pumping and storage reservoirs, water lines 16 inches and larger, wastewater lines 10 inches and larger.
-
Impact fee dollars for Water and Wastewater have been invested in these areas.
Water System
Pump Modifications at NE Pump Station $1,020,000 Transmission main Greenwood to Lincoln $4,114,746 Total $5,134,746 As of 08/31/18
Water Distribution
District 1 Water main at NW 25th to 27th Street at Hwy. 34 267,354 District 1 Water main at W Adams, NW 48th - 63rd, NW 56th South 439,791 District 1 Water main at Holdrege, NW 40th - 48th 30,133 District 1 Water main at West "O" St., NW 56th - West 119,646 District 2 Water main at NW 12th to 27th Street at Hwy. 34 195,952 District 2 Water main at NW 12th, US 34 to Fletcher 32,272 District 2 Water mains at NW 12th to Fletcher at Hwy. 34 100,000 District 2 Water mains at NW 12th Loop 2,071 District 2 Water main at Fletcher from 14th to 17th 150,751 District 2 Water main at 14th, Julesburg to Alvo 210,359 District 3 Water main at N 56th, Fletcher to Arbor Rd 34,199 District 3 Water main at Arbor Road, from 52nd to 56th 99,995 District 3 Water main at Arbor Road, from 56th to 70th 6,558 District 4 Water main at Adams, 81st to 87th 202,418 District 4 Water main at Waterford Estates 451,464 District 4 Water main at 98th, Holdrege to "O" Street 33,096 District 4 Water main at Adams, 91st to 98th & Leighton 75,070 District 4 Water main at "O" St. 83rd to 98th 29,591 District 5 Water main at 98th Pine Lake Rd to Yankee Hill 640,818 District 5 Water main at Pioneers, 87th to Thorns 90,375 District 5 Water main at Van Dorn, 84th to 91st 255,793 District 6 Water main at 27th to 56th Yankee Hill to Union 267,829 District 6 Water main at Rokeby, 27th to 40th 54,310 District 6 Water main at 70th/Pine Lake/Yankee Hill 72,752 District 6 Water main at Yankee Hill, from 56th to 84th 883,120 District 6 Water main at South 70th, Lilee Drive to Rebel Lane 259,873 District 6 Water main at 84th, Yankee Hill to Rokeby 51,883 District 6 Water main at Rokeby, 77th to 84th 44,744 District 7 Water main at W Van Dorn, Coddington East 3,084 District 7 Water main at Folsom/Pioneers/Old Cheney 458,622 Total $5,563,923 As of 08/31/18
Wastewater
48" Upper SE Trunk Sewer Main at Salt Valley Basin 287,684 36" Relief Trunk Sewer Main at Beal Slough Basin 1,531,096 30" West "O" Trunk Sewer Extension 310,000 66" Trunk Sewer Main at Steven's Creek Basin 4,639,101 36" NE Salt Creek Basin 70,000 Total $6,837,881 As of 08/31/18