Pine Lake from 61st to Highway 2 Widening and Safety Improvement Project
The City of Lincoln began the Pine Lake Road widening and safety improvement project in March 2018. This project was necessary to increase the capacity of the roadway as a part of the increasing development in southeast Lincoln.
One lane of travel in each direction was opened to traffic on December 24, 2019. All lanes of travel were opened in each direction on Pine Lake Road on January 30, 2020.
Project Highlights
Pine Lake Road was widened to four lanes from S 61st Street to Highway 2
The curve and slope of the hill between S 75th Street and Highway 2 was reduced to improve sight distance
The S 70th Street and Pine Lake Road intersection was reconstructed with a roundabout
The railroad crossing east of Pine Lake Park will be rebuilt with crossing gates in 2020
The Beal Slough culvert was upgraded and will include a trail undercrossing for a future pedestrian trail
A new culvert was constructed under Blanchard Boulevard and will include a trail undercrossing
The intersection of Blanchard Boulevard and Pine Lake Road was reconstructed with a roundabout
Additional culverts beneath S 70th Street and Pine Lake Road were reconstructed to increase capacity
Sidewalks were built along the roadway and street lighting was upgraded
Project Area
- Project Area
Public Involvement
- Open House – Tuesday, February 13, 2018
- 6:00 – 7:30 p.m.
- Humann Elementary School, 6720 Rockwood Lane
- Open House – Wednesday, December 16, 2015
- 6:00 – 8:00 p.m.
- Humann Elementary School, 6720 Rockwood Lane
Project Contacts
-
Randy Saathoff, Construction Project Manager
City of Lincoln, LTU Project Delivery
Phone: 402-440-6067
Email: rsaathoff@lincoln.ne.gov -
Casey Thompson, Project Manager
K2 Construction
Phone: 402-560-8558
Email: cthompson@k2construction.biz