Display Records
Order NumberDateSubject
813507/3/2008RIGHT OF WAY CONTRACT WITH TREVOR J. AND TRACIE L. HASENKAMP IN CONNECTION WITH A PORTION OF LOT 1, BLOCK 3, HARTLAND ESTATES, BEING THE WEST A STREET SANITARY SEWER PROJECT 700-430.
813497/3/2008BID AND CONTRACT WITH BOB & DON'S PLUMBING AND JOHN HENRY'S PLUMBING HEATING & AC FOR THE UNIT PRICE CONTRACT FOR PLUMBING LARGER THAN 2 INCHES. (SPEC 08-169)
813487/3/2008BID OF HAWKINS WATER TREATMENT GROUP FOR FURNISHING THE ANNUAL SUPPLY OF CASTIC SODA BEADS FOR WASTEWATER IN THE AMOUNT OF .47 PER POUND OR 33,000 POUNDS AT $15,510. (SPEC 08-172 ADDENDUM 1)
813477/3/2008FINAL CHANGE ORDER #1 TO THE CONTRACT WITH SAK CONSTRUCTION LLC FOR ADDITIONAL WORK ASSOCIATED WITH THE LINCOLN WASTEWATER SYSTEM'S SANITARY SEWER LINER INSERTION PROJECT 705-000 FOR THE ADDITIONAL AMOUNT OF $17,910.69. THE FINAL CONTRACT AMOUNT IF HEREBY REVISED TO $111,035.34 AND SHALL NOT BE EXCEEDED WITHOUT FURTHER AUTHORIZATION. (REF: EO 81026)
813467/3/2008RIGHT OF WAY CONTRACT WITH LINCOLN RIDGE POINTE LLC, IN CONNECTION WITH A PORTION OF OUTLOT A, RIDGE POINT 2ND ADDITION, BEING THE PINE LAKE ROAD AND HELEN WITT TRAFFIC SIGNAL PROJECT 702-132, TRACT 5.
813457/3/2008AGREEMENT WITH JUSTIN J. VILLAFANE, DDS, TO PROVIDE DENTAL SERVICES TO THE LINCOLN-LANCASTER COUNTY HEALTH DEPARTMENT FOR THE TIME PERIOD JULY 1, 2008 TO JUNE 30, 2009 FOR THE SUM OF $52 PER HOUR.
813447/3/2008RIGHT OF WAY CONTRACT WITH AILEEN ELIKER IN CONNECTION WITH LOT 3, BLOCK 4, AIRPORT HEIGHTS 1ST ADDITION, BEING THE WEST ADAMS AND NORTHWEST 56TH STREET WIDENING AND IMPROVEMENT PROJECT 701-906, TRACT 6.
813437/3/2008PARTIAL RELEASE OF REAL PROPERTY MORTGAGE, RELEASING ANY AND ALL LIEN OR INTEREST THE CITY MAY HAVE IN PROPERTY AT 1803 NORTH 24 STREET TO AFFORDABLE HOUSING PARTNERS I, LP.
813427/3/2008SUBSTITUTION OF TRUSTEE APPOINTING ERNEST R. PEO III AS SUCCESSOR TRUSTEE UNDER THE TRUST DEED EXECUTED BY JAWAD K. & HAYFA H. AL-HELFI, AS TRUSTOR, IN WHICH THE CITY OF LINCOLN IS NAMED BENEFICIARY AND JAMES D. FAIMON AS TRUSTEE, AND RECORDED IN THE REGISTER OF DEED OF LANCASTER COUNTY AS INSTRUMENT NO. 2000-022200. IT IS FURTHER REQUESTED THAT ERNEST R. PEO III, AS SUCCESSOR TRUSTEE, EXECUTE THE DEED OF RECONVEYANCE RELEASING ANY AND ALL LIEN OR INTEREST WHICH THE CITY MAY HAVE UNDER INSTRUMENT NO. 2000-022200 IN REAL PROPERTY AT 322 NORTH 30 STREET.
813417/3/2008RIGHT OF WAY CONTRACT WITH GERALD L. JACOBSEN II IN CONNECTION WITH LOT 4, BLOCK 28, ARNOLD HEIGHTS REPLAT, BEING THE WEST ADAMS AND NORTHWEST 56TH STREET WIDENING AND IMPROVEMENT PROJECT 701-906, TRACT 27.
813407/3/2008RIGHT OF WAY CONTRACT WITH JOHN D. AND TWYLA MORTON IN CONNECTION WITH A PORTION OF LOT 17, IRREGULAR TRACT LOCATED IN THE SOUTHWEST QUARTER OF SECTION 13, TOWNSHIP 9 NORTH, RANGE 7 EAST OF THE 6TH PM BEING THE SOUTH 98TH STREET WIDENING PROJECT 700-845, PINE LAKE ROAD TO OLD CHENEY ROAD.
813397/3/2008WARRANTY DEED IN CONNECTION WITH THE SALE OF PROPERTY AT 201 WEST E STREET TO DAVID C LANGE IN THE AMOUNT OF $1,000.
813387/3/2008REAL ESTATE SALES AGREEMENT WITH DAVID C. LANGE IN CONNECTION WITH THE SALE OF PROPERTY AT 201 WEST E STREET IN THE AMOUNT OF $1,000.
813377/2/2008BID AND CONTRACT WITH AMSAN NEBRASKA INC DBA NOGG CHEMICAL AND PAPER FOR FURNISHING ANNUAL SUPPLY OF CUSTODIAL SUPPLIES/HARD GOODS TO BE PURCHASED THROUGH INTERGOVERNMENTAL PURCHASING (UNIVERSITY OF NEBRASKA CONTRACT 9966) EFFECTIVE APRIL 22, 2004 THROUGH OCTOBER 12, 2008.
813367/3/2008SUBDIVISION AGREEMENT WITH SOUTH RIDGE VILLAGE LLC FOR THE FINAL PLAT OF SOUTH RIDGE VILLAGE 11TH ADDITION.
813357/3/2008WEEKLY DISBURSEMENT OF FUNDS FOR THE WEEK ENDED JUNE 26, 2008.
813347/3/2008SUBDIVISION AGREEMENT ACCEPTING BOND NO. 012014224 FROM WEST POINT LLC, AS PRINCIPAL, AND LIBERTY MUTUAL INSURANCE COMPANY, AS SURETY, IN THE PENAL SUM OF $250 AS THE REQUIRED SECURITY TO GUARANTEE THE INSTALLATION OF SIDEWALKS WITHIN WEST POINT BUSINESS PARK 1ST ADDITION.
813337/3/2008ADDENDUM TO THE ORIGINAL AGREEMENT WITH HANSEN INFORMATION TECHNOLOGIES INC WHICH PROVIDES A ONE YEAR EXTENSION OF THE ANNUAL SERVICE AND MAINTENANCE FOR HANSEN 8 ASSET MANAGEMENT, WORK MANAGEMENT, MAP DRAWER, CUSTOMER SERVICE AND GEOADMINISTRATOR. COVERAGE TERM COMMENCES FEBRUARY 1, 2008 AND WILL CONTINUE IN FORCE THROUGH JANUARY 31, 2009 FOR A TOTAL COST OF $43,452. (REF: EO 76995)
813327/3/2008AMENDMENT NO 7 T CONTRACT W/OLSSON ASSOCIATES FOR ADDITIONAL DESIGN SERVICES ON THE WEST BRANCH SALT CREEK TRUNK (UPPER SOUTHWEST SALT CREEK TRUNK SEWER EXTENSION PROJECT 502-457) FOR AN ADDITIONAL AMOUNT OF $21,117 AND A REVISED TOTAL OF $961,195. RE: EO'S 71401, 72346, 73324, 77306, 78970, & 80084.
813317/3/2008SUBDIVISION AGREEMENT AND THE AGREEMENT FOR ESCROW OF SECURITY FUND WITH ALPHA DEVCO LLC TO GUARANTEE THE INSTALLATION OF SIDEWALKS, SETTING PERMANENT MONUMENTS, PLANTING OF STREET TREES, AND INSTALLATION OF STREET NAME SIGNS WITHIN THE FINAL PLAT OF WILLOW SPRINGS 3RD ADDITION.
123