Display Records
Order NumberDateSubject
809464/10/2008RENEWAL OF SPECIFICATION/CONTRACT WITH LAYNE WESTERN COMPANY INC FOR WELL PARTS, PUBLIC WORKS. (SPEC 07-145)
809454/10/2008APPROVING THE REQUEST OF EIGER CORPORATION TO DESIGN AND CONSTRUCT A TURN LANE IN SOUTH 91 STREET FOR APPIAN WAY REGIONAL CENTER.
809444/10/2008CONSULTANT AGREEMENT W/OLSSON ASSOCATES, INC FOR PROFESSIONAL ENGINEERING AND PLANNING SERVICES AND ASSISTANCE IN THE DEVELOPMENT OF A WEST HAYMARKET TRANSPORATION, ENVIRONMENTAL AND UTILITIES PLAN (TEUP). (08-027)
809434/10/2008INTERLOCAL AGREEMENT W/NEBRASKA BOARD OF REGENTS FOR THE PROVISION OF BUS SERVICE IN CONJUNCTION WITH THE UNL TRANSPORTATION PROGRAM. THIS IS THE FINAL RENEWAL YEAR OF THE TWO, ONE-YEAR RENEWAL OPTIONS, AND WILL BEGIN AUGUST 21, 2008.
809424/10/2008APPOINTMENT OF DAVE TINIUS TO THE PLUMBING CODE BOARD OF APPEALS FOR A ONE YEAR TERM EXPIRING JANUARY 31,2009.
809414/10/2008REAPPOINTMENT OF MATT MORRISSEY AND TIMOTHY WENTZ TO THE PLUMBING CODE BOARD OF APPEALS FOR ONE YEAR TERMS EXPIRING JANUARY 31, 2009.
809404/10/2008SUBDIVISION AGREEMENT WITH R G HALL, LP HELD TO GUARANTEE THE INSTALLATION OF STREET NAME SIGNS AND PERMANENT MARKERS IN BEAVER CREEK ADDITION.
809394/10/2008AGREEMENT FOR PROFESSIONAL OR TECHNICAL SERVICES WITH HANNA KEELAN ASSOCIATES PC TO PROVIDE A BLIGHT AND SUBSTANDARD STUDY FOR THE 70TH & FLETCHER STREET AREA FOR A LUMP SUM PAYMENT OF $5,000 WHICH IS FUNDED BY FOUR PRIVATE ENTITIES IN THE STUDY AREA.
809384/10/2008SUBDIVISION AGREEMENT AND AGREEMENT FOR ESCROW OF SECURITY FUND WITH AUTOMOTIVE PROPERTIES LLC AND TALTON K & MARY JOY ANDERSON HELD TO GUARANTEE INSTALLATION OF SIDEWALKS AND PLANTING OF STREET TREES WITHIN THE FINAL PLAT OF NORTH CREEK COMMERCIAL PARK 1ST ADDITION.
809374/10/2008WEEKLY DISBURSEMENT OF FUNDS FOR THE WEEK ENDING APRIL 3, 2008.
809364/10/2008AGREEMENT W/THE SCHEMMER ASSOCIATES FOR CONSTRUCTION DESIGN SERVICES FOR A 36" WATER DISTRIBUTION MAIN IN YANKEE HILL ROAD FROM 56 TO 84 STREET FOR THE AMOUNT OF $276,504.03. REF: 803-613.
809354/10/2008PROPOSAL (CONTRACT) BETWEEN LINCOLN FIRE & RESCUE AND CENTER FOR PUBLIC SAFETY EXCELLENCE TO CONDUCT THE SELF ASSESSMENT FACILITATION AND ACCREDITATION PROJECT.
809344/10/2008PROCLAMATION OF ELECTION PROCLAIMING THAT A SPECIAL ELECTION WILL BE HELD IN THE CITY OF LINCOLN ON TUESDAY, MAY 13, 2008, FOR THE PURPOSE OF SUBMITTING TO THE ELECTORS THE FOLLOWING ISSUE: CHARTER AMENDMENT - AMEND ARTICLE IV, SECTION 12; ARTICLE VII, SECTIONS 1 AND 2; AND ARTICLE VII, SECTION 5 OF THE CHARTER TO REQUIRE THE MAYOR TO MAKE OR APPROVE THE EXECUTION OF PURCHASES AND CONTRACTS GREATER THAN $25,000; TO AUTHORIZE THE MAYOR TO DELEGATE THE EXECUTION OF CONTRACTS AND PURCHASES OF LESS THAN $25,000; AND TO AUTHORIZED THE CONSTRUCTION OF PUBLIC WORKS AND UTILITIES PROJECTS BY COMPANIES WHEN THE CITY SUBSIDY DOES NOT EXCEED $100,000.
809334/9/2008BID AND CONTRACT W/CLEAN HARBORS ENVIRONMENTAL SERVICES FOR HOUSEHOLD HAZARDOUS WASTE COLLECTIONS, HAZARDOUS WASTE SERVICES FOR CITY/COUNTY DEPARTMENTS AND LIMITED SMALL BUSINESS HAZARDOUS WASTE SERVICES. (08-066) 6/5/08 - REPLACED BY THE COST PROPOSAL APPROVED BY DO828.
809324/9/2008GRANT CONTRACT W/FRIENDSHIP HOME FOR $7,500 TO ASSIST IN PROVIDING SERVICES.
809314/9/2008CHANGE ORDER #8 TO CONTRACT WITH HAWKINS CONSTRUCTION COMPANY FOR NITRIFICATION IMPROVEMENTS AT THE THERESA STREET WASTEWATER TREATMENT FACILITY FOR THE DECREASED AMOUNT OF $327,213. THE TOTAL CONTRACT AMOUNT IS REVISED TO $18,250,252.00 AND SHALL NOT BE EXCEEDED WITHOUT FURTHER AUTHORIZATION. REF: PROJECT #502-420.
809304/9/2008AGREEMENT FOR PROFESSIONAL ENGINEERING SERVICES W/JEO CONSULTING GROUP, INC FOR THE DESIGN OF TURNER DITCH CHANNEL IMPROVEMENTS. THIS DESIGN OF THIS PROJECT WILL FOCUS ON STABILIZING THE TURNER DITCH BANK SOLVING STANDING WATER ISSUES AND PROVIDING ACCESS FOR FUTURE MAINTENANCE OF THE CHANNEL DOWNSTREAM OF 40 STREET WITH EXPENDITURES NOT TO EXCEED $53,930.00. REF: PROJECT 702-204.
809294/9/2008SETTLEMENT AGREEMENT W/JUDDS BROTHERS CONSTRUCTION COMPANY RELATED TO THE NORTHEAST PUMPING STATION IMPROVEMENTS PROJECT FOR AN AMOUNT OF $134,748 IN LIQUIDATED DAMAGES. THE SETTLEMENT SHALL BE DEDUCTED FROM THE FINAL PAYMENT ON THE CONTRACT. RE: EO 72810.
809284/9/2008PARTIAL RELEASE OF SANITARY SEWER EASEMENT RELEASING A 388.8 SQUARE FOOT PORTION OF LOTS 1 AND 2, BOULDER RIDGE 1ST ADDITION FROM THE PLATTED 30 FOOT SANITARY EASEMENT GRANTED THROUGH THE FINAL PLAT OF BOULDER RIDGE 1ST ADDITION RECORDED ON 9/7/07 AS INSTRUMENT NO. 2007-045579.
809274/9/2008INTERLOCAL AGREEMENT W/NEBRASKA DEPARTMENT OF ENVIRONMENTAL QUALITY FOR STATE/LOCAL SECTION 103 FUNDS FOR THE HEALTH DEPARTMENT AIR QUALITY PROGRAM FOR AN ADDITIONAL $20,000 FOR 1/1/08 TO 12/31/08.
123