77866 | 11/22/2006 | RETAINER RELEASED ($4,400) TO RIDGE DEVELOPMENT COMPANY HELD FOR THE CONSTRUCTION OF PAVING IN PINE LAKE HEIGHTS SOUTH 8TH ADDITION IN CONFORMANCE W/THE CONDITIONS OF EO 66290. |
77865 | 11/22/2006 | RETAINER RELEASED ($0) TO THE UNIVERSITY OF NEBRASKA FOR THE CONSTRUCTION OF BUS/COACH DROP OFF LANE AT 14 STREET FOR UNL PARKING GARAGE HELD TO GUARANTEE THE EO 69176. |
77864 | 11/22/2006 | RETAINER RELEASED ($800) TO BEGI, LLC HELD TO GUARANTEE THE CONSTRUCTION OF MEDIAN OPENING ON CORNHUSKER HIGHWAY AT NORTH 23 STREET. |
77863 | 11/22/2006 | RETAINER RELEASED ($1,500) TO F PACE WOODS II HELD TO GUARANTEE THE CONSTRUCTION OF STORM SEWERS IN ROLLING HILLS RIDGE IN CONFORMANCE W/THE CONDITIONS OF EO 68931. |
77862 | 11/22/2006 | SURETY RELEASED ($300) TO B & K ENTERPRISES, INC HELD TO GUARANTEE THE INSTALLATION OF THE PERMANENT SURVEY MONUMENTS IN EDENTON NORTH 15TH ADDITION IN CONFORMANCE W/THE CONDITIONS OF EO 73514. |
77861 | 11/22/2006 | RETAINER RELEASED ($16,700) TO RIDGE DEVELOPMENT COMPANY HELD TO GUARANTEE THE PAVING IN PINE LAKE HEIGHTS SOUTH 6TH ADDITION IN CONFORMANCE W/THE CONDITIONS OF EO 64677. |
77860 | 11/22/2006 | SURETY RELEASED ($57,700) TO STERLING HILLS, LLC HELD TO GUARANTEE THE CONSTRUCTION OF THE PRIVATE STREET PAVING IN STERLING HILLS 1ST ADDITION IN CONFORMANCE W/THE CONDITIONS OF EO 71797. |
77859 | 11/22/2006 | RETAINER RELEASED ($2,000) T0 STONE BRIDGE CREEK, LLC HELD TO GUARANTEE THE CONSTRUCTION OF SANITARY SEWERS IN STONE BRIDGE CREEK 1ST ADDITION, PHASE II IN CONFORMANCE W/THE CONDITIONS OF EO 67791. |
77858 | 11/22/2006 | RETAINER RELEASED ($1,500) TO RIDGE DEVELOPMENT COMPANY HELD TO GUARANTEE THE SANITARY SEWERS IN STONE RIDGE ESTATES, LOT 82, IT, IN CONFORMANCE W/THE CONDITIONS OF EO 71025. |
77857 | 11/22/2006 | SURETY RELEASED ($87,600) TO A C HOLDINGS, LLC HELD TO GUARANTEE THE SANITARY SEWERS IN APPLE'S WAY RESIDENTIAL ADDITION IN CONFORMANCE W/THE CONDITIONS OF EO 76556. |
77856 | 11/22/2006 | APPROVING THE REQUEST OF PEOPLES CITY MISSION HOME TO CONSTRUCT WATER MAIN IN VACATED R STREET BETWEEN NORTH 1 AND 2 STREET. |
77855 | 11/22/2006 | RIGHT OF WAY CONTRACT W/NEBRASKA SCHOOL OF GYMNASTICS, SOUTH, INC, IN CONNECTION W/A PORTION OF LOT 1, PIONEER SUBDIVISION FOR THE PIONEER BOULEVARD WIDENING PROJECT 700-019, ANTELOPE CREEK TO PAGODA LANE, TRACT 5. THIS EO SUPERCEDES EO 77185 APPROVED 9/6/06. |
77854 | 11/22/2006 | SUB-CONTRACT AMENDMENT W/NEBRASKA DEPARTMENT OF INSURANCE FOR ADDITIONAL FUNDING IN THE AMOUNT OF $8,000 FOR THE FUNDING OF THE SHIIP OFFICE LOCATED WITHIN THE LIFE OFFICE TO ACHIEVE THE MISSION OF THE COUNSELING PROGRAM FOR THE CITIZENS OF CITY OF LINCOLN FROM 9/1/06 THROUGH 3/31/07. |
77853 | 11/22/2006 | APPROVING THE REQUEST OF US FOODS, LLC, RICK WILLIAMS, TO CONSTRUCT WATER MAIN ABANDONMENT IN NORTHWEST 39 STREET FROM WILKINS TO SUPERIOR STREETS. |
77852 | 11/22/2006 | SUB-CONTRACT AMENDMENT W/NEBRASKA DEPARTMENT OF INSURANCE FOR ADDITIONAL FUNDING IN THE AMOUNT OF $4,000 FOR THE FUNDING OF THE SHIIP OFFICE LOCATED WITHIN THE LIFE OFFICE TO ACHIEVE THE MISSION OF THE COUNSELING PROGRAM FOR THE CITIZENS OF THE CITY OF LINCOLN FROM 9/1/06 THRUOGH 3/31/07. |
77851 | 11/22/2006 | APPROVING THE REQUEST OF MARK HANSEN TO CONSTRUCT PUBLIC SANITARY SEWER IN 3400-3600 WEST O STREET. |
77850 | 11/22/2006 | SUB GRANT CONTRACT W/NEBRASKA DEPARTMENT OF INSURANCE FOR THE FUNDING OF THE SHIIP OFFICE LOCATED WITHIN THE LIFE OFFICE TO ACHIEVE THE MISSION OF THE COUNSELING PROGRAM FOR THE CITIZENS OF CITY OF LINCOLN FROM APRIL 1, 2006 THROUGH MARCH 31, 2007. |
77849 | 11/22/2006 | BID AND CONTRACT W/CB & I CONSTRUCTORS, INC FOR CHENEY BOOSTER WATER STORAGE RESERVOIR PROJECT 701-825 FOR THE SUM OF $2,893,000. (06-263) |
77848 | 11/21/2006 | AGRMT W/CAROLYN C CHANEY & ASSOCIATES, INC TO PROVIDE LEGISLATIVE SERVICES AS THE CITY'S WASHINGTON ASSISTANT FOR A 12 MONTH PERIOD AT A COST OF $77,774.40 PLUS UP TO A MAXIMUM OF $3,000 FOR REIMBURSABLE EXPENSES. |
77847 | 11/21/2006 | SURETY RELEASED ($135,600) TO RESERVE DEVELOPMENT, LLC HELD TO GUARANTEE THE CONSTRUCTION OF STREET PAVING IN CARDWELL RESERVE ADDITION IN CONFORMANCE W/THE CONDITIONS OF EO 76228. |
|