Order Number | Date | Subject |
78292 | 1/25/2007 | BID OF CAL PIPE SECURITY BOLLARDS FOR FURNISHING STAINLESS STEEL BOLLARDS FOR WESTFIELD SHOPPING CENTER FOR THE SUM OF $27,488. (SPEC 06-330, OR 9047) |
78291 | 1/23/2007 | RESCINDING EO 76999 DATED 8/07/06 APPROVING REQUEST OF RIDGE DEVELOPMENT COMPANY FOR THE CONSTRUCTION OF STORM SEWERS IN PINE RIDGE 1ST ADDITION. |
78290 | 1/23/2007 | CHANGE ORDER #1 WITH NEMAHA LANDSCAPE CONSTRUCTION FOR ANTELOPE CREEK TRAIL PHASE I FOR AN INCREASE OF $8,885.84 AND THE COMPLETION DATE SHALL BE OCTOBER 31, 2006. |
78289 | 1/23/2007 | AGREEMENT WITH ARROW STAGE LINES TO PROVIDE MOTORCOACH SERVICES TO INDIAN CAVE STATE PARK IN SHUBERT, NEBRASKA FOR NORTHEAST ACTIVAGE CENTER TRIP ON NOVEMBER 2,2006 FOR A TOTAL COST OF $590. |
78288 | 1/23/2007 | ADDENDUM TO AGREEMENT WITH A TO Z PRINTING FOR ANNUAL REQUIREMENTS FOR QUICK COPY & OFFSET PRINTING SERVICES FOR THE CITY OF LINCOLN AND LANCASTER COUNTY FOR VARIOUS CITY AND COUNTY DEPARTMENTS. (SPEC 05-007) |
78287 | 1/23/2007 | RESCINDING EO 77000 DATED 8/07/06 APPROVING REQUEST OF RIDGE DEVELOPMENT COMPANY FOR THE CONSTRUCTION OF PAVING IN PINE RIDGE 1ST ADDITION. |
78286 | 1/22/2007 | APPLICATION FOR FEDERAL ASSISTANCE, ASSURANCES AND RELATED DOCUMENTS FOR THE CITY TO OBTAIN FEDERAL ASSISTANCE IN THE AMOUNT OF $824,500 RELATED TO THE DEVELOPMENT AND MAINTENANCE OF A NATIONAL URBAN SEARCH AND RESCUE RESPONSE SYSTEM AND TO PROVIDE LOCAL QUALIFIED PERSONNEL UNDER THE US DEPARTMENT OF HOMELAND SECURITY FEDERAL RESPONSE PLAN. |
78285 | 1/22/2007 | BID AND CONTRACT WITH K2 CONSTRUCTION FOR THE WATER MAIN PROJECT 700-300, BEING IN HOLDREGE FROM 70 TO 73 STREET IN THE AMOUNT OF $61,903.01 IN ACCORDANCE WITH THE PLANS AND CONTRACT DOCUMENTS. |
78284 | 1/22/2007 | APPROVING APPLICATION FOR FUNDING TO THE STATE OF NEBRASKA DEPARTMENT OF ROADS FOR TECHNICAL STUDIES ASSISTANCE FROM THE FEDERAL TRANSIT ADMINISTRATION, US DEPARTMENT OF TRANSPORTATION FOR FISCAL YEAR 2006-07 IN THE AMOUNT OF $87,132.00, TO BE MATCHED BY CITY FUNDS IN THE AMOUNT OF $21,783. |
78283 | 1/22/2007 | APPROVING REQUEST OF DUBOIS, LLC TO CONSTRUCT WATER MAIN IN GRAND TERRACE ADDITION. |
78282 | 1/22/2007 | AUTHORIZATION TO PURCHASE WITH INSIGHT PUBLIC SECTOR, INC FURNISHING 25 LAPTOP COMPUTERS AND ACCESSORIES THRU A CONTRACT WITH ADMIN MINNESOTA (EO 74649 AND 9142 OR) FOR THE SUM OF $121,945. |
78281 | 1/22/2007 | SURETY RELEASED ($8,609) TO ASPEN BUILDERS, INC HELD TO GUARANTEE CONSTRUCTION OF ORNAMENTAL LIGHTING IN ASPEN RIDGE 3RD ADDITION IN CONFORMANCE WITH THE CONDITIONS OF EO 72068. |
78280 | 1/22/2007 | SURETY RELEASED ($1,500) TO LINCOLN FEDERAL SAVINGS BANK HELD TO GUARANTEE INSTALLATION OF PERMANENT SURVEY MONUMENTS IN HORIZON BUSINESS CENTER ADDITION IN CONFORMANCE WITH THE CONDITIONS OF ORDINANCE #11978. |
78279 | 1/22/2007 | SURETY RELEASED ($575) TO N & K INVESTMENTS HELD TO GUARANTEE INSTALLATION OF STREET NAME SIGNS IN CORNHUSKER CROSSING ADDITION IN CONFORMANCE WITH THE CONDITIONS OF EO 51902. |
78278 | 1/22/2007 | SURETY RELEASED ($230) TO GOOD SHEPHERD PRESBYTERIAN CHURCH HELD TO GUARANTEE INSTALLATION OF STREET NAME SIGNS IN CROWN POINTE ESTATES 3RD ADDITION IN CONFORMANCE WITH THE CONDITIONS OF RESO PC-00229. |
78277 | 1/22/2007 | SURETY REDUCED WITH REGARD TO THE CONSTRUCTION OF SIDEWALKS IN STERLING HILLS 1ST ADDITION, BY STERLING HILLS, LLC, IN CONFORMANCE WITH THE CONDITIONS OF EO 71797, WHICH REQUIRED A SURETY POSTED IN THE AMOUNT OF $55,200 TO GUARANTEE THE SAID CONSTRUCTION WHICH IS NOW 90% COMPLETED AND THE BOND TO GUARANTEE THE CONSTRUCTION IS HEREBY REDUCED 75% OR TO A NEW SUM OF $13,800. |
78276 | 1/22/2007 | ANNUAL MAINTENANCE RENEWAL CONTRACT WITH KRAUTER-BOSN SERVICE COMPANY FOR COMPUTER ROOM AIR CONDITIONERS AND STEAM HUMIDIFIERS EFFECTIVE UNTIL JANUARY 10, 2008. |
78275 | 1/22/2007 | RETAINER RELEASED ($10,000) TO EIGER CORP HELD TO GUARANTEE CONSTRUCTION OF TURN LANES AT 91 & HIGHWAY 2 IN CONFORMANCE WITH THE CONDITIONS OF EO 65930. |
78274 | 1/22/2007 | CHANGE ORDER #5 ON THE CONTRACT WITH NEMAHA LANDSCAPE CONSTRUCTION, INC FOR THE CONSTRUCTION OF THE ANTELOPE CREEK TRIBUTARY CREEK STABILIZATION PROJECT 702-211 RESULTING IN A DECREASE OF $14,102.32 AND THE COMPLETION DATE SHALL BE OCTOBER 24, 2006. |