DO999 | 7/31/2008 | SURETY REDUCED WITH REGARD TO THE CONSTRUCTION OF SIDEWALK IN HERITAGE LAKES 1ST ADDITION BY HERITAGE LAKES, LLC IN CONFORMANCE W/THE CONDITIONS OF EO 69369 WHICH REQUIRED A SURETY POSTED IN THE AMOUNT OF $18,700 TO GUARANTEE THE SAID CONSTRUCTION, IS NOW 53% COMPLETED AND THE BOND TO GUARANTEE THE CONSTRUCTION IS HEREBY REDUCED 50% OR TO A NEW SUM OF $9,350. |
DO998 | 7/30/2008 | AMENDMENT NO 2 TO CONTRACT W/BLACK & VEATCH CORPORATION TO PROVIDE ADDITIONAL CONSTRUCTION PHASE SERVICES FOR CONSTRUCTION ACTIVITIES AT THE NORTHEAST PUMP STATION NOT TO EXCEED $3,600. TOTAL CONTRACT SHALL NOT EXCEED $538,200. |
DO997 | 7/30/2008 | AGREEMENT W/SCOTT WEIHE, PGA GOLF PROFESSIONAL TO PROVIDE PROFESSIONAL SERVICES AT JIM AGER MEMORIAL JUNIOR GOLF COURSE. |
DO996 | 7/29/2008 | RETAINER RELEASED ($100) TO KNUTSON COMPANY LLC HELD TO GUARANTEE THE WATER MAINS IN WEST PARK 1ST ADDITION IN CONFORMANCE W /THE CONDITIONS OF EO 74386. |
DO995 | 7/29/2008 | RETAINER RELEASED ($400) TO KNUTSON COMPANY LLC HELD TO GUARANTEE WATER MAINS IN 5500 SOUTH 84 STREET IN CONFORMANCE W/THE CONDITIONS OF EO 74533. |
DO994 | 7/29/2008 | RETAINER RELEASED ($3,400) TO NEBRASKA HOUSING RESOURCES HELD TO GUARANTEE THE WATER MAINS IN OLD MILL VILLAGE 2ND ADDITION IN CONFORMANCE W/THE CONDITIONS OF EO 72694. |
DO993 | 7/29/2008 | RETAINER RELEASED ($1,600) TO PINE LAKE DEVELOPMENT, LLC HELD TO GUARANTEE THE WATER MAINS IN VINTAGE HEIGHTS 23RD ADDITION IN CONFORMANCE W/THE CONDITIONS OF EO 74915. |
DO992 | 7/29/2008 | RETAINER RELEASED ($1,400) TO PINE LAKE DEVELOPMENT, LLC HELD TO GUARANTEE THE WATER MAINS IN VINTAGE HEIGHTS 25TH ADDITION IN CONFORMANCE W/THE CONDITIONS OF EO 75020. |
DO991 | 7/29/2008 | RETAINER RELEASED ($5,900) TO PINE LAKE DEVELOPMENT LLC HELD TO GUARANTEE THE WATER MAINS IN VINTAGE HEIGHTS 22ND ADDITION IN CONFORMANCE W/THE CONDITIONS OF EO 72623. |
DO990 | 7/29/2008 | RETAINER RELEASED ($12,000) TO RIDGE DEVELOPMENT COMPANY HELD TO GUARANTEE THE WATER MAINS IN BIG THOMPSON CREEK 1ST ADDITION IN CONFORMANCE WITH THE CONDITIONS OF EO 71013. |
DO989 | 7/29/2008 | SURETY RELEASED ($10,000 REMAINING PORTION) TO PINE LAKE DEVELOPMENT, LLC HELD TO GUARANTEE THE CONSTRUCTION OF SIDEWALK IN VINTAGE HEIGHTS 3RD ADDITION IN CONFORMANCE W/THE CONDITIONS OF RESO PC-00449. |
DO988 | 7/29/2008 | SURETY REDUCED WITH REGARD TO THE CONSTRUCTION OF SIDEWALK IN VINTAGE HEIGHTS 14TH ADDITION BY PINE LAKE DEVELOPMENT LLC IN CONFORMANCE W/THE CONDITIONS OF RESOLUTION PC-00808 WHICH REQUIRED A SURETY POSTED IN THE AMOUNT OF $66,000 TO GUARANTEE THE SAID CONSTRUCTION IS NOW 90% COMPLETED AND THE BOND TO GUARANTEE THE CONSTRUCTION IS HEREBY REDUCED 75% TO A NEW SUM OF $16,500. |
DO987 | 7/29/2008 | RETAINER RELEASED ($300) TO EIGER CORP. HELD TO GUARANTEE THE WATER MAINS IN APPIAN WAY REGIONAL CENTER, PHASE II IN CONFORMANCE W/THE CONDITIONS OF EO 73002. |
DO986 | 7/29/2008 | RETAINER RELEASED ($5,100) TO HAUSMANN DEVELOPMENT, LLC HELD TO GUARANTEE THE WATER MAINS IN WOODLAND VIEW IN CONFORMANCE W/THE CONDITIONS OF EO 73041. |
DO985 | 7/29/2008 | RETAINER RELEASED ($3,700) TO IRONWOOD ESTATES, LLC HELD TO GUARANTEE THE WATER MAINS IN RAVENWOOD DEVELOPMENT IN CONFORMANCE W/THE CONDITIONS OF EO 74331. |
DO984 | 7/29/2008 | RETAINER RELEASED ($6,000) TO THE LINKS AT LINCOLN HELD TO GUARANTEE THE WATER MAINS FOR THE LINKS @ LINCOLN IN CONFORMANCE W /THE CONDITIONS OF EO 75395. |
DO983 | 7/29/2008 | RETAINER RELEASED ($1,300) TO SCOTT ANDERSON HELD TO GUARANTEE THE WATER MAINS IN ANDERSON'S PLACE 1ST ADDITION IN CONFORMANCE W/THE CONDITIONS OF EO 75357. |
DO982 | 7/28/2008 | CHANGE ORDER NO 1 TO CONTRACT W/LOTTMAN CARPENTER CONSTRUCTION FOR THE CONSTRUCTION OF THE HOLMES LAKE SOUTHWEST TRIBUTARY STREAM STABILITY PROJECT 702-250. COMPLETION DATE OF THIS PROJECT SHALL NOW BE 9/15/08. |
DO981 | 7/28/2008 | CHANGE ORDER NO 2 TO CONTRACT W/VAN KIRK BROTHERS CONSTRUCTION FOR THE WELL REPLACEMENT, ASHLAND WELL FIELD, PHASE 2 FOR A DECREASE OF $22,500 AND A NEW TOTAL OF $767,783.00. |