54900 | 5/6/1998 | SURETY POSTED ($425)(TIME CERTIFICATE # 27679) FROM CORNHUSKER BANK TO GUARANTEE THE INSTALLATION OF SIDEWALKS IN CROUSE ADDITION. |
54899 | 5/6/1998 | PROMISSORY NOTE & DISCLOSURE STATEMENT W/TERESA WILLIAMS FOR A $14,995 FIRST HOME LOAN FOR THE PURCHASE & REHABILITATION OF PROPERTY AT 1100 NORTH 53 STREET. (41-5674C) |
54898 | 5/6/1998 | PROMISSORY NOTE & DISCLOSURE STATEMENT W/EUNICE BARNES FOR A $1,240.50 0% EMERGENCY REPAIR DEFERRED LOAN FOR THE REHABILITATION OF PROPERTY AT 1612 SOUTH 10 STREET. (41-5674C) |
54897 | 5/6/1998 | SUBORDINATION AGRMT. AGREEING TO SUBORDINATE THE EXISTING DEEDS OF TRUST HELD BY THE CITY IN THE AMOUNTS OF $5,094.50 EXECUTED BY JACK & DENISE FAZEL ON MAY 11, 1993 TO THE LIEN OF OCWEN FEDERAL BANK ON PROPERTY AT 2824 Q STREET. (41-5674C) |
54896 | 5/6/1998 | SURETY RELEASED ($6,900) TO L.C. DEVELOPMENT COMPANY HELD TO GUARANTEE THE CONSTRUCTION OF ORNAMENTAL LIGHTING FOR PRIVATE STREETS IN LINCOLN CROSSING 1ST ADD., A FINAL PLAT APPROVED BY ORD. 16332. |
54895 | 5/6/1998 | FINAL PLAT, SUB. AGRMT., AGRMT. FOR ESCROW OF SECURITY FUND, & AGRMT. FOR USE OF ESCROW FUNDS FOR BARRINGTON PARK SECOND ADDITION ON PROPERTY LOCATED IN LOT 21, BLOCK 3, & OUTLOT B, BARRINGTON PARK ADD., LOCATD IN THE SOUTHEAST QUARTER OF SEC. 10, T9N, R7E OF THE 6TH P.M. AS FULLY DESCRIBED IN RESOLUTION PC-00424 DATED APRIL 22, 1998. FILED REGISTER OF DEEDS 5/20/98; INSTRUMENT #98-024090. |
54894 | 5/6/1998 | LICENSE BOND FROM LAND CONSTRUCTION COMPANY AS PRINCIPAL & INLAND INSURANCE COMPANY AS SURETY IN THE PENAL SUM OF $5,000 IS ACCEPTED AS SECURITY TO GUARANTEE EROSION CONTROL & RESTORATION OF TOP SOIL & VEGETATION REQUIRED AS A CONDITION OF SPECIAL PERMIT 1723. |
54893 | 5/6/1998 | LICENSE BOND FROM LAND CONSTRUCTION COMPANY AS PRINCIPAL & INLAND INSURANCE CO. AS SURETY IN THE PENAL SUM OF $5,000 AS THE SECURITY TO GUARANTEE EROSION CONTROL & RESTORATION OF TOP SOIL & VEGETATION AS A CONDITION OF SPECIAL PERMIT 1724. |
54892 | 5/6/1998 | BID OF LIFE SCIENTIFIC, INC. FOR LABORATORY GLASSWARE WASHER FOR PUBLIC WORKS LABS FOR THE SUM OF $12,122.00. (36-7279) |
54891 | 5/6/1998 | BID OF MATT FRIEND TRUCK EQUIPMENT, INC. ($35,401) & ALL TRUCK EQUIPMENT ($11,598) FOR FURNISHING TRUCK BODIES. |
54890 | 5/6/1998 | SURETY RELEASED ($188,000) TO RIDGE DEVELOPMENT CO. HELD TO GUARANTEE CONSTRUCTION OF PAVING TO SERVE THE RIDGE 13TH ADD. HELD IN CONFORMANCE W/THE CONDITIONS OF EO 49893. |
54889 | 5/6/1998 | SURETY RELEASED ($88,700) TO CHENEY RIDGE PARTNERS HELD TO GUARANTEE CONSTRUCTION OF SANITARY SEWER TO SERVE CHENEY RIDGE ADD. HELD IN CONFORMANCE W/THE CONDITIONS OF EO 53497. |
54888 | 5/6/1998 | SURETY RELEASED ($26,600) TO ST. PAUL UNITED METHODIST CHURCH HELD TO GUARANTEE CONSTRUCTION OF SANITARY SEWER TO SERVE 11TH & M STREETS HELD IN CONFORMANCE W/THE CONDITIONS OF EO 53345. |
54887 | 5/6/1998 | SURETY RELEASED ($81,000) TO WEST GATE, INC. HELD TO GUARANTEE CONSTRUCTION OF PAVING TO SERVE CRIPPLE CREEK SOUTH 7TH ADD. HELD IN CONFORMANCE W/THE CONDITIONS OF EO 52764. |
54886 | 5/6/1998 | SURETY RELEASED ($11,400) TO PINE LAKE HEIGHTS PARTNERSHIP HELD TO GUARANTEE CONSTRUCTION OF ORNAMENTAL LIGHTING TO SERVE THE PINE LAKE HEIGHTS 11TH ADD. HELD IN CONFORMANCE W/THE CONDITIONS OF EO 52101. |
54885 | 5/6/1998 | RETAINER RELEASED ($800) TO RIDGE DEVELOPMENT CO. HELD TO GUARANTEE CONSTRUCTION OF ORNAMENTAL LIGHTING TO SERVE THE RIDGE 13TH ADD. HELD IN CONFORMANCE W/THE CONDITIONS OF EO 49890. |
54884 | 5/6/1998 | RETAINER RELEASED ($500) TO PINE LAKE HEIGHTS LIMITED PARTNERSHIP HELD TO GUARANTEE THE CONSTRUCTION OF ORNAMENTAL LIGHTING IN PINE LAKE HEIGHTS 9TH ADD. HELD IN CONFORMANCE W/CONDITIONS OF EO 50923. |
54883 | 5/6/1998 | RETAINER RELEASED ($600) TO WEST GATE, INC. HELD TO GUARANTEE CONSTRUCTION OF ORNAMENTAL LIGHTING TO SERVE CRIPPLE CREEK SOUTH 1ST ADD. - PHASE II HELD IN CONFORMANCE W/THE CONDITIONS OF EO 51342. |
54882 | 5/6/1998 | RETAINER RELEASED ($200) TO PINE LAKE HEIGHTS LIMITED PARTNERSHIP HELD TO GUARANTEE CONSTRUCTION OF ORNAMENTAL LIGHTING TO SERVE PINE LAKE HEIGHTS 3RD ADD. IN CONFORMANCE W/TH CONDITIONS OF EO 47240. |
54881 | 5/6/1998 | BID OF ELECTRIC CONSTRUCTION FOR STREET CONVERSION TO TWO-WAY TRAFFIC IN TRAFFIC PROJECT # 700201 IN P STREET IN THE AMOUNT OF $521,644.79. |
|