Order Number | Date | Subject |
75496 | 2/3/2006 | RETAINER RELEASED ($4,400) TO ALLEGRINI COMMONS ONE, LLC HELD TO GUARANTEE THE SANITARY SEWER IN ALLEGRINI TERRACE VINTAGE HEIGHTS 3RD ADDITION IN CONFORMANCE W/THE CONDITIONS OF EO 67764. |
75495 | 2/3/2006 | RETAINER RELEASED ($600) TO LINCOLN NORTH CREEK, LLC HELD TO GUARANTEE THE SANITARY SEWER IN NORTH CREEK BUSINESS PARK IN CONFORMANCE W/THE CONDITIONS OF EO 67769. |
75494 | 2/3/2006 | DEED OF RECONVEYANCE RELEASING ANY AND ALL LIEN OR INTEREST IN PROPERTY AT 333 SOUTH 27 STREET TO SHARON K HEUSMAN. |
75493 | 2/3/2006 | RETAINER RELEASED ($8,750) TO PINE LAKE DEVELOPMENT LLC HELD TO GUARANTEE THE WATER MAIN IN VINTAGE HEIGHTS 11TH ADDITION IN CONFORMANCE W/THE CONDITIONS FO EO 64489. |
75492 | 2/3/2006 | AGRMT. BETWEEN THE CITY/COUNTY HEALTH DEPT. & LINCOLN ACTION PROGRAM, INC, EARLY HEAD START FOR THE PERIOD FEBRUARY 1, 2006 TO JANUARY 31, 2007. LAP WILL REIMBURSE LLCHD $833 PER MONTH FOR THE DURATION OF THIS AGRMT. |
75491 | 2/3/2006 | ADDENDUM TO AGREEMENT W/RODGERS & MCDONALD PRINTING & GRAPHICS FOR PROVIDING PRINTING AND PREPARATION FOR DISTRIBUTION THROUGH THE UNITED STATES POSTAL SERVICE (USPS). THIS CHANGES THE METHOD OF DELIVERY OF INSERTION INTO OUR LOCAL NEWSPAPER & REDUCES THE NUMBER OF COPIES FROM 107,000 PIECES TO APPROXIMATELY 61,000. REF: EO #75025. |
75490 | 2/3/2006 | AGRMT. BETWEEN THE CITY/COUNTY HEALTH DEPT. & NEBRASKA HEALTH AND HUMAN SERVICES SYSTEM FOR $75,000 FOR THE HEPATITIS B PROGRAM AND THE IMMUNIZATION ACTION PLAN FOR THE PERIOD JANUARY 1, 2006 TO DECEMBER 31, 2006. |
75489 | 2/3/2006 | SURETY REDUCED WITH REGARD TO THE CONSTRUCTION OF SIDEWALK IN HIMARK ESTATES 1ST ADDITION BY HIMARK DEVELOPMENT LLC IN CONFORMANCE W/THE CONDITIONS OF RESOLUTION PC-00520 WHICH REQUIRED A SURETY POSTED IN THE AMOUNT OF $18,700 TO GUARANTEE THE SAID CONSTRUCTION IS NOW 97% COMPLETED AND THE BOND TO GUARANTEE THE CONSTRUCTION IS HEREBY REDUCED 75% OR TO A NEW SUM OF $4,675. |
75488 | 2/3/2006 | SURETY REDUCED WITH REGARD TO THE CONSTRUCTION OF SIDEWALK IN HIMARK ESTATES ORIGINAL ADDITION BY HIMARK DEVELOPMENT COMPANY IN CONFORMANCE W/THE CONDITIONS OF RESOLUTION PC-00498 WHICH REQUIRED A SURETY POSTED IN THE AMOUNT OF $40,300 TO GUARANTEE THE SAID CONSTRUCTION IS NOW 70% COMPLETED AND THE BOND TO GUARANTEE THE CONSTRUCTION IS HEREBY REDUCED 50% OR TO A NEW SUM OF $20,150. |
75487 | 2/3/2006 | SURETY REDUCED WITH REGARD TO THE CONSTRUCTION OF SIDEWALK IN IRONGATE ESTATES 2ND ADDITION BY D & M DEVELOPMENT & HIMARK DEVELOPMENT INC IN CONFORMANCE W/THE CONDITIONS OF EO #72979 WHICH REQUIRED A SURETY POSTED IN THE AMOUNT OF $8,500 TO GUARANTEE THE SAID CONSTRUCTION IS NOW 77% COMPLETED AND THE BOND TO GUARANTEE THE CONSTRUCTION IS HEREBY REDUCED 75% OR TO A NEW SUM OF $2,125. |
75486 | 2/3/2006 | SURETY REDUCED WITH REGARD TO THE CONSTRUCTION OF SIDEWALK IN HIMARK ESTATES 2ND ADDITION BY HIMARK DEVELOPMENT IN CONFORMANCE W/THE CONDITIONS OF RESOLUTION PC-525 WHICH REQUIRED A SURETY POSTED IN THE AMOUNT OF $16,800 (CASH) TO GUARANTEE THE SAID CONSTRUCTION IS NOW 92% COMPLETED AND THE BOND TO GUARANTEE THE CONSTRUCTION IS HEREBY REDUCED 75% OR TO A NEW SUM O F $4,200. |
75485 | 2/3/2006 | SURETY REDUCED WITH REGARD TO THE CONSTRUCTION OF SIDEWALK IN IRONGATE ESTATES 1ST ADDITION BY HIMARK DEVELOPMENT AND D & M DEVELOPMENT IN CONFORMANCE W/THE CONDITIONS OF EO #72248 WHICH REQUIRED A SURETY POSTED IN THE AMOUNT OF $5,700 TO GUARANTEE THE SAID CONSTRUCTION IS NOW 62% COMPLETED AND THE BOND TO GUARANTEE THE CONSTRUCTION IS HEREBY REDUCED 50% OR TO A NEW SUM OF $2,850. |
75484 | 2/3/2006 | SURETY REDUCED WITH REGARD TO THE CONSTRUCTION OF SIDEWALK IN IRONGATE ESTATES ADDITION BY DRU LAMMLE IN CONFORMANCE W/THE CONDITIONS OF RESOLUTION PC-00620 WHICH REQUIRED A SURETY POSTED IN THE AMOUNT OF $25,000 TO GUARANTEE THE SAID CONSTRUCTION IS NOW 77% COMPLETED AND THE BOND TO GUARANTEE THE CONSTRUCTION IS HEREBY REDUCED 75% OR TO A NEW SUM OF $6,250. |
75483 | 2/3/2006 | SURETY REDUCED WITH REGARD TO THE CONSTRUCTION OF SIDEWALK IN HIMARK ESTATES 3RD ADDITION BY HIMARK DEVELOPMENT, INC IN CONFORMANCE W /THE CONDITIONS OF RESO PC-00619 WHICH REQUIRED A SURETY POSTED IN THE AMOUNT OF $40,000 TO GUARANTEE THE SAID CONSTRUCTION IS NOW 93% COMPLETED AND THE BOND TO GUARANTEE THE CONSTRUCTION IS HEREBY REDUCED 75% OR TO A NEW SUM OF $10,000. |
75482 | 2/3/2006 | SURETY RELEASED ($1,500) TO M & S CONSTRUCTION HELD TO GUARANTEE THE CONSTRUCTION OF A PEDESTRIAN EASEMENT SIDEWALK IN ASHLEY HEIGHTS ADDITION IN CONFORMANCE W/THE CONDITIONS OF EO 62973. |
75481 | 2/3/2006 | SURETY RELEASED ($11,100) TO RIDGE DEVELOPMENT COMPANY HELD TO GUARANTEE THE CONSTRUCTION OF PAVING FOR THE EXTENSION OF ENTERPRISE DRIVE IN KING RIDGE 1ST ADDITION IN CONFORMANCE W/THE CONDITIONS OF RESO PC-00472. |
75480 | 2/3/2006 | SURETY RELEASED ($4,050) TO MANZITTO, INC HELD TO GUARANTEE THE INSTALLATION OF THE PERMANENT SURVEY MONUMENTS IN HIMARK ESTATES 9TH ADDITION IN CONFORMANCE W/THE CONDITIONS OF EO 71660. |
75479 | 2/3/2006 | SURETY RELEASED ($900) TO RAYMOND SNYDER HELD TO GUARANTEE THE INSTALLATION OF PERMANENT SURVEY MONUMENTS IN HIMARK ESTATES 6TH ADDITION IN CONFORMANCE W/THE CONDITIONS OF RESO PC-00652. |
75478 | 2/3/2006 | RETAINER RELEASED ($805) TO HIGHLANDS DEVELOPMENT CORPORATION HELD TO GUARANTEE THE INSTALLATION OF STREET NAME SIGNS IN HIGHLANDS EAST ORIGINAL ADDITION IN CONFORMANCE W/THE CONDITIONS OF ORDINANCE 16132. |
75477 | 2/3/2006 | SURETY REDUCED WITH REGARD TO CONSTRUCTION OF THE PRIVATE ROADWAY PAVING IN THOMPSON CREEK COMMERCIAL 1ST ADDITION BY THOMPSON CREEK LLC IN CONFORMANCE W/ THE CONDITIONS OF EO 74943 WHICH REQUIRED A SURETY POSTED IN THE AMOUNT OF $39,300 TO GUARANTEE SAID CONSTRUCTION IS NOW 46% COMPLETE AND THE PARTIAL SURETY AMOUNT OF $18,400 IS HEREBY RELEASED REDUCING THE REMAINING SURETY TO A NEW SUM OF $20,900. |
|